Cat A or Cat B Office Fit-Out? A UK Tenant’s Handover Checklist
An office described as Cat A can look almost ready on a letting tour. The ceiling is finished, the lights are on and there is power on the floor. The more revealing question is what happens when your team adds two meeting rooms, a tea point and desks for the people who come in on a busy Tuesday. Before you compare UK office refurbishment quotes, give each bidder the same description of the floor you receive and the workplace you need.

A furnished test layout makes it easier to see which partitions and services a tenant needs to change. View an office planning cutaway.
Read the handover specification alongside the floor plan
Category A generally describes the basic landlord fit-out. It may include services distributed across the floor, lighting and ceiling or floor systems. Category B describes the fit-out for the occupier, such as partitions, a reception area, furniture and meeting-room technology. The precise package varies. Ask for a dated handover specification, drawings showing services and a list of items the outgoing tenant will remove.
On a second visit, take the proposed handover plan with you. A glazed meeting room may look worth keeping until you learn it belongs to the outgoing tenant. Equally, the landlord may be willing to retain something already marked for removal. Mark each item as confirmed, awaiting a decision or requiring a survey. Record who can settle the question and by when.
Test a busy working day on the plan
List the activities that need privacy, quiet or equipment and who uses them at the same time. A team of 24 with twelve desks occupied most days might still need three separate video calls at ten o’clock. Map those calls as well as the desks. A simple test layout will show whether you need three enclosed rooms, smaller call spaces or a change to how the existing rooms are booked.
Now overlay the proposed walls on the lighting and ventilation drawings. A new partition may divide an existing lighting or control zone. Ask the building-services engineer to identify changes for the proposed layout. A price for the glazed walls alone leaves you guessing what it will take for the rooms to work.
Compare the same four decisions in each quote
Take one space at a time and write down what stays, what moves, what you buy and who confirms it. For a tea point, the landlord may confirm a capped water connection while the tenant’s contractor prices the run to the sink. If the connection location is unconfirmed, identify it as an allowance with an owner. Two bids using different assumptions about the same pipe are difficult to compare.
Ask each bidder to separate their design fee, physical works, furniture and specialist packages. Include move-in essentials such as data connections and the meeting-room screen installation. The British Council for Offices’ Guide to Fit-Out covers procurement and how the finished workplace is used. Both topics belong in the brief while the floor plan is still flexible.
Price the existing fit-out as a genuine option
For a second-hand Cat B floor, mark the joinery, partitions and furniture that suit the test layout. Ask bidders to price reusing the existing partitions and furniture against a replacement layout that meets the same meeting-room and occupancy brief. Have the property adviser and landlord confirm which alterations and end-of-lease arrangements apply to that floor. Your final comparison should show the work you are buying, the amount still provisional and the decisions that could affect your move date.
Project references
Related reading. Should You Lease a Shell-and-Core or Fitted Office in Dubai?
Send me the landlord’s handover specification, the current plan and the activities your team needs to accommodate. Working remotely from Dubai, I can scope an office interior design and test-layout package around the decisions still open.
Explore Interior Design in my portfolio.





Comments